Safe and Livable Communities through well-maintained infrastructure and facilities.
Post Date:11/30/2022 9:58 AM
ABOUT THE PROJECT
The Lake Drive Storm Drain Project encompasses replacement
of 2,000 feet of corrugated metal pipe from Lake Drive to
Interstate 5. It was originally constructed by the County in
1982 and is in need of replacement due to its deteriorated
condition and numerous sinkholes that have developed. The
surrounding property and trails are owned and maintained by
The Nature Collective. Eroded sediment was removed from
San Elijo Lagoon under emergency permit in 2020/2021.